Al Maktoum International: 25 years to Phase 1
From the first runway in 2007 to a 150M-passenger Phase 1 in 2032: cargo and passenger launches, a $32bn plan, launches paused from 2018, the AED 128bn relaunch, and the rail links scheduled around it.

Timeline
Phase 1 opens in 2032, 25 years after the first runway
- 2007Runway 1 completeDone
- Jun 2010Cargo flightsDone
- Oct 2013Passenger flightsDone
- Sep 2014$32bn planDone
- Oct 2018On hold (launches paused)Done
- Apr 2024AED 128bn planDone
- 30 Sep 2026Etihad Rail in DubaiDone
- Late 2027Runway 2 opensScheduled
- 2030–31High-speed railScheduled
- 2032Phase 1 opens · 150M passengersScheduled
Sources: Dubai Airports; Gulf News; Airport Technology; Etihad Rail; IRJ (2010–2026).