DLD's project register lists 345 projects by Emaar across 25 communities: 202 finished, 118 active, 24 not started, 1 pending. 329 of them have sales this year on DataDXB.
Dubai Land Department, 1 Nov 2026
Registered companies
Dubai Land Department, 1 Nov 2026
- Al Aryam Phase One L.L.C5 projects
- Al Aryam Phase Two L.L.C3 projects
- Dubai Creek Harbour L.L.C27 projects
- Dubai Hills Estate L.L.C55 projects
- DWTC Emaar L.L.C3 projects
- Emaar Bawadi (L L C)2 projects
- Emaar Development P.J.S.C.110 projects
- Emaar Dubai South DWC LLC35 projects
- Emaar Properties (P.J.S.C)61 projects
- Mina Rashid Properties L.L.C22 projects
- Old Town Views L.L.C1 project
- The Lagoons Phase One L.L.C21 projects
Communities
Dubai Land Department, 1 Nov 2026
Projects by Emaar in DLD's project register, grouped by community, with DLD's status, progress and units.
Dubai Hills Estate55 projects
- Acacia At Park HeightsFinished · 551 units
- Address HillcrestFinished
- Address Residences l Dubai Hills EstateActive · 26.48% complete · 582 units
- Club DriveFinished · 529 units
- Club PlaceActive · 68.82% complete · 473 units
- Club Villas at Dubai HillsFinished
- CollectiveFinished · 477 units
- Collective 2.0Finished · 495 units
- Dubai Hills - Hills Grove CommunityFinished
- Dubai Hills - Hills View CommunityFinished
- ElviraFinished · 902 units
- Fairway VistasFinished
43 more projects in Dubai Hills Estate
- Golf GrandFinished · 329 units
- Golf GroveFinished
- Golf HillsideActive · 65.78% complete · 185 units
- Golf PlaceFinished
- Golf Place llFinished
- Golf Suites - Dubai HillsFinished · 216 units
- Golf villeFinished · 308 units
- GreencrestActive · 1.2% complete · 195 units
- Greenside ResidenceActive · 93.32% complete · 490 units
- Hills ParkFinished · 450 units
- HillsedgeActive · 25.55% complete · 406 units
- Lime GardensFinished · 293 units
- Majestic VistasFinished
- MapleFinished
- Maple 2Finished
- Maple IIIFinished
- MULBERRY at PARK HEIGHTSFinished · 676 units
- Palace Residences Dubai Hills EstateActive · 50.72% complete · 962 units
- Palace Residences Hillside AActive · 7.87% complete · 360 units
- Palace Residences Hillside BNot started · 0% complete · 287 units
- Palm HillsFinished
- Park FieldFinished · 306 units
- Park GateActive · 90.29% complete
- Park Gate 2Active · 55.15% complete
- Park Heights IFinished · 275 units
- Park Heights IIFinished · 557 units
- Park HorizonFinished · 306 units
- Park LaneActive · 55.39% complete · 854 units
- Park PointFinished · 338 units
- Park RidgeFinished · 1,056 units
- ParklandActive · 50.02% complete · 209 units
- Parkside HillsActive · 68.29% complete · 370 units
- Parkside ViewsFinished · 389 units
- Parkway VistasFinished
- ParkwoodActive · 15% complete · 488 units
- RosehillActive · 7.83% complete · 555 units
- SidraFinished
- Sidra 2Finished
- Sidra 3Finished
- SocioFinished · 336 units
- Vida Residences Club PointActive · 43.52% complete · 672 units
- Vida Residences Dubai Hills EstateFinished · 217 units
- Vida Residences HillsideActive · 10% complete · 500 units
Dubai Creek Harbour48 projects
- 17 Icon BayFinished · 383 units
- Address Harbour PointFinished · 813 units
- Address Residences l Dubai Creek HarbourActive · 26.44% complete · 326 units
- AeonActive · 90.04% complete · 262 units
- AlberoActive · 11% complete · 479 units
- AltanActive · 11.06% complete · 479 units
- AltusActive · 64.2% complete · 283 units
- ArloActive · 35.42% complete · 434 units
- Creek BayActive · 0.62% complete · 766 units
- Creek Beach - BayshoreFinished · 305 units
- Creek Beach - BreezeFinished · 202 units
- Creek Beach - Canopy - MoorFinished · 444 units
36 more projects in Dubai Creek Harbour
- Creek Beach - GroveFinished · 269 units
- Creek Beach - LotusFinished · 270 units
- Creek Beach - OrchidFinished · 208 units
- Creek Beach - RosewaterFinished · 211 units
- Creek Beach - Savanna-Cedar-MangroveFinished · 595 units
- Creek Beach - SummerFinished · 305 units
- Creek Beach - SunsetFinished · 151 units
- Creek Beach - SurfFinished · 173 units
- Creek Beach - VIDA ResidencesFinished · 233 units
- Creek CrescentFinished · 230 units
- Creek EdgeFinished · 564 units
- Creek GateFinished · 498 units
- Creek HavenActive · 0.87% complete · 594 units
- Creek HorizonFinished · 559 units
- Creek PalaceFinished · 337 units
- Creek RiseFinished · 547 units
- Creek WatersActive · 81.08% complete · 453 units
- Creek Waters 2Active · 81.84% complete · 455 units
- Creekside 18Finished · 506 units
- DLD project 1826Finished · 291 units
- Harbour GateFinished · 517 units
- Harbour ViewsFinished · 784 units
- Island Park IFinished · 160 units
- Island Park IIFinished · 160 units
- Lyvia by PalaceActive · 4.77% complete · 481 units
- MontivaActive · 5.85% complete · 475 units
- OriaActive · 71.1% complete · 163 units
- Palace Residences - Dubai Creek HarbourFinished · 592 units
- Palace Residences - NorthFinished · 340 units
- Palace Residences Creek BlueActive · 20.52% complete · 512 units
- SilvaActive · 10.16% complete · 437 units
- The Cove llFinished · 806 units
- The Dubai Creek ResidencesFinished · 924 units
- The GrandFinished · 574 units
- ValiaNot started · 0% complete · 492 units
- ValoActive · 66.05% complete · 291 units
Downtown Dubai32 projects
- 29 BoulevardFinished · 750 units
- Act One | Act TwoFinished · 787 units
- Bd Boulevard PlazaFinished · 217 units
- Blvd CrescentFinished · 365 units
- Blvd HeightsFinished · 558 units
- Boulevard PointFinished · 449 units
- Burj CrownFinished · 433 units
- Burj DubaiFinished · 28 units
- Burj Khalifa TowersFinished · 1,078 units
- Burj RoyaleFinished · 602 units
- Burj ViewsFinished · 737 units
- Burj VistaFinished · 790 units
20 more projects in Downtown Dubai
- Claren 1Finished · 321 units
- Dd Boulevard CentralFinished · 424 units
- Dd Stand PointFinished · 537 units
- Downtown ViewsFinished · 479 units
- Downtown Views IIFinished · 1,515 units
- ForteFinished · 927 units
- GrandeFinished · 906 units
- Il PRIMOFinished · 137 units
- Opera GrandFinished · 306 units
- The Address - The BlvdFinished · 543 units
- The Address Dubai OperaFinished · 873 units
- The Address Residence - Sky ViewFinished · 708 units
- The Address Residence Fountain Views IIFinished · 289 units
- The Address Residence Fountain Views IIIFinished · 209 units
- The Address Residence-Fountain ViewsFinished · 286 units
- The Dubai MallFinished · 456 units
- THE RESIDENCE | Burj KhalifaFinished · 35 units
- The St. Regis Residences, Downtown DubaiActive · 76.05% complete · 1,108 units
- Vida Dubai MallFinished · 621 units
- Vida Residence Downtown DubaiFinished · 347 units
The Valley28 projects
- The Valley - AlanaActive · 81.56% complete
- The Valley - AlvaNot started · 0% complete
- The Valley - Alva 2Not started · 0% complete
- The Valley - Alva 3Not started · 0% complete
- The Valley - AveliaNot started · 0.27% complete
- The Valley - AvenaActive · 24.47% complete
- The Valley - Avena 2Active · 42.89% complete
- The Valley - EdenFinished
- The Valley - EleaActive · 22.02% complete
- The Valley - EloraFinished
- The Valley - ElvaActive · 25.86% complete
- The Valley - Farm GardensFinished
16 more projects in The Valley
- The Valley - Farm Gardens 2Active · 59.08% complete
- The Valley - Farm GroveActive · 10% complete
- The Valley - Farm Grove 2Active · 9.77% complete
- The Valley - KaiaActive · 19.13% complete
- The Valley - LilliaFinished
- The Valley - NimaActive · 80.02% complete
- The Valley - OraniaFinished
- The Valley - OvelleActive · 2.36% complete
- The Valley - RivanaActive · 95.24% complete
- The Valley - RiveraActive · 3.94% complete
- The Valley - TaliaFinished
- The Valley - VeloraActive · 50.07% complete
- The Valley - Velora 2Active · 40.28% complete
- The Valley - VeneraActive · 51.7% complete
- The Valley - VinderaActive · 1.98% complete
- The Valley-NaraFinished
Dubai World Central24 projects
- Fairway VillasFinished
- Fairway Villas 2Active · 92.16% complete
- Fairway Villas 3Active · 48.52% complete
- Golf AcresActive · 3.47% complete · 158 units
- Golf DaleNot started · 0.27% complete · 200 units
- Golf EdgeNot started · 0% complete · 179 units
- Golf FieldsNot started · 0% complete · 181 units
- Golf HillsActive · 3.67% complete · 204 units
- Golf Hills 2Active · 4.16% complete · 204 units
- Golf LaneActive · 30.05% complete
- Golf MeadowActive · 4.54% complete · 188 units
- Golf TrailsNot started · 0% complete · 161 units
12 more projects in Dubai World Central
- Golf ValeNot started · 0% complete · 262 units
- Golf VergeActive · 4.22% complete · 204 units
- GreenridgeActive · 35.6% complete
- GreenspointActive · 42.9% complete
- Greenspoint 2Active · 40.09% complete
- Greenview 3Finished
- GreenvilleActive · 46.02% complete
- Greenville 2Active · 47.31% complete
- GreenwayActive · 39.06% complete
- Greenway 2Active · 34.37% complete
- Grove RidgeNot started · 0% complete · 193 units
- Vista RidgeNot started · 0% complete · 198 units
Mina Rashid22 projects
- AureaNot started · 0.22% complete · 172 units
- AvonleaActive · 63.71% complete · 163 units
- BaylineActive · 61.31% complete · 151 units
- Baystar by VIDAActive · 6.3% complete · 328 units
- ClearpointActive · 45.05% complete · 478 units
- Fior 1Not started · 0% complete · 184 units
- Fior 2Not started · 0% complete · 216 units
- Marina Place 1Active · 4.23% complete · 162 units
- Marina Place 2Active · 1.52% complete · 180 units
- Marina ViewsActive · 7.09% complete · 554 units
- Ocean CoveActive · 17.93% complete · 233 units
- Ocean PointActive · 26.95% complete · 217 units
10 more projects in Mina Rashid
- Ocean StarActive · 30.46% complete · 155 units
- Ocean ViewsActive · 6.18% complete · 78 units
- Pier Point 1Active · 8.27% complete · 122 units
- Pier Point 2Active · 8.48% complete · 121 units
- Porto ViewActive · 6.26% complete · 115 units
- SeagateFinished · 302 units
- SeascapeActive · 79.13% complete · 395 units
- Sera 1Not started · 0.04% complete · 203 units
- Sera 2Not started · 0.04% complete · 183 units
- SunridgeFinished · 130 units
Emirates Living16 projects
- Emirates HillsFinished
- Emirates Living - Springs 1Finished
- Emirates Living - Springs 2Finished
- Emirates Living - Springs 3Finished
- Emirates Living - Springs 4Finished
- Emirates Living - Springs 5Finished
- Emirates Living - Springs 6Finished
- Emirates Living - Springs 7Finished
- Emirates Living - Springs 8Finished
- Emirates Living - Springs 9Finished
- Emirates Living - Springs 10Finished
- Emirates Living - Springs 11Finished
4 more projects in Emirates Living
- Emirates Living - Springs 12Finished
- Emirates Living - Springs 14Finished
- Emirates Living - Springs 15Finished
- The Maisonettes At The MontgomeriePending · 100% complete
Arabian Ranches III15 projects
- Arabain Ranches lll - BlissFinished
- Arabian Ranches III - JOYFinished
- Arabian Ranches III - SpringFinished
- Arabian Ranches III - SUNFinished
- Arabian Ranches lll - AnyaFinished
- Arabian Ranches lll - Anya 2Finished
- Arabian Ranches lll - Bliss 2Finished
- Arabian Ranches lll - CayaFinished
- Arabian Ranches lll - Elie SaabFinished
- Arabian Ranches lll - Elie Saab llFinished
- Arabian Ranches lll - JuneFinished
- Arabian Ranches lll - June 2Finished
3 more projects in Arabian Ranches III
- Arabian Ranches lll - MayFinished
- Arabian Ranches lll - RayaFinished
- Arabian Ranches lll - RubaFinished
Dubai Harbour13 projects
- Address The BayActive · 70.08% complete · 448 units
- BayviewActive · 63.02% complete · 690 units
- Beach IsleFinished · 397 units
- Beach MansionFinished · 495 units
- Beach VistaFinished · 466 units
- Beachgate by AddressFinished · 252 units
- Grand Bleu Tower interiors by Elie SaabFinished · 639 units
- Marina VistaFinished · 625 units
- Palace Beach ResidenceFinished · 552 units
- Palace by the BeachNot started · 0% complete · 861 units
- SeapointActive · 36.78% complete · 674 units
- Sunrise BayFinished · 461 units
1 more project in Dubai Harbour
- THE BRISTOL Emaar BeachfrontActive · 5.83% complete · 229 units
Dubai Investment Park Second13 projects
- Grand Polo - Chevalia EstateActive · 2.28% complete
- Grand Polo - Chevalia Estate 2Active · 4.09% complete
- Grand Polo - Chevalia FieldsActive · 10.03% complete
- Grand Polo - EquestraActive · 1.02% complete
- Grand Polo - EquiterraActive · 0.83% complete
- Grand Polo - Equiterra 2Active · 1.04% complete
- Grand Polo - MonturaActive · 11.08% complete
- Grand Polo - Montura 2Active · 5.01% complete
- Grand Polo - Montura 3Active · 1.06% complete
- Grand Polo - SelvaraActive · 2.81% complete
- Grand Polo - Selvara 2Active · 4.04% complete
- Grand Polo - Selvara 3Active · 2.98% complete
1 more project in Dubai Investment Park Second
- Grand Polo - Selvara 4Active · 2.88% complete
Arabian Ranches II11 projects
- AR II - Reem CommunityFinished
- AR II CameliaFinished
- AR II Camelia 2Finished
- Arabian Ranches - Lila CommunityFinished
- Arabian Ranches - Palma CommunityFinished
- Arabian Ranches - Rasha CommunityFinished
- Arabian Ranches - Samara CommunityFinished
- Arabian Ranches - Yasmin CommunityFinished
- Arabian Ranches- Azalea CommunityFinished
- Arabian Ranches- Rosa CommunityFinished
- Arabian Ranches-Casa CommunityFinished
Emaar South11 projects
- Golf LinksFinished
- Golf PointActive · 4.78% complete · 590 units
- Golf ViewsFinished · 291 units
- GreenviewFinished
- Greenview 2Finished
- ParksideFinished
- Parkside 2Finished
- Parkside 3Finished
- UrbanaFinished · 324 units
- Urbana IIFinished · 236 units
- Urbana IIIFinished · 372 units
The Oasis11 projects
- Mareva 2 The OasisActive · 1.32% complete
- Mareva The OasisActive · 2.05% complete
- The Oasis - Address Villas - TierraActive · 6.81% complete
- The Oasis - LavitaActive · 20.13% complete
- The Oasis - MirageActive · 46.94% complete
- The Oasis - Palace Villas - OstraActive · 6.54% complete
- The Oasis - PalmieraActive · 81.72% complete
- The Oasis - Palmiera 2Active · 77.11% complete
- The Oasis - Palmiera 3Active · 72.62% complete
- The Oasis - Palmiera CollectiveActive · 1.33% complete
- Valoria The OasisActive · 1.12% complete
Dubai Marina8 projects
- 5242Finished · 493 units
- Dm Marina PlazaFinished · 170 units
- Dubai Marina MallFinished · 452 units
- Marina CoveActive · 5.68% complete · 227 units
- Marina QuaysFinished · 450 units
- Marina ShoresActive · 87.18% complete · 447 units
- Park IslandsFinished · 733 units
- VIDA Residences Dubai MarinaFinished · 364 units
Mira8 projects
- Reem - Mira Oasis CommunityFinished
- Reem - Mira Oasis Community Phase 2Finished
- Reem - Mira Oasis Community Phase 3Finished
- Reem-Mira Community Ph 1Finished
- Reem-Mira Community Ph 2Finished
- Reem-Mira Community Ph 3Finished
- Reem-Mira Community Ph 4Finished
- Reem-Mira Community Ph5Finished
The Lakes8 projects
- Golf HeightsFinished · 281 units
- The HillsFinished · 590 units
- The Lakes - Deema 1Finished
- The Lakes Deema 2Finished
- The Lakes Deema 3Finished
- The Lakes Deema 4Finished
- The Lakes GhadeerFinished
- The Lakes ZulalFinished
Arabian Ranches I7 projects
- Alma-2Finished
- Arabian Ranches - Alvorada IIIFinished
- Arabian Ranches -La Avenida IFinished
- AseelFinished
- DLD project 1021Finished
- Golf HomesFinished
- La Avenida-2Finished
The Heights Country Club & Wellness5 projects
- Faro 2 The HeightsNot started · 0% complete
- Faro The HeightsNot started · 0% complete
- Salva The HeightsActive · 0.5% complete
- Serro 2 The HeightsActive · 0.5% complete
- Serro The HeightsActive · 0.5% complete
The Greens3 projects
Expo City2 projects
- Terra GardensNot started · 0.08% complete · 561 units
- Terra WoodsNot started · 0% complete · 824 units
Al Yelayiss 21 project
- MaysanActive · 36.7% complete · 576 units
Al Yelayiss 41 project
- Teema 1 & Teema 2Active · 8.79% complete
Arabian Ranches Polo Club1 project
- Polo HomesFinished
Business Bay1 project
- Avarra by PalaceNot started · 0.08% complete · 694 units
Dubai South1 project
- Terra HeightsActive · 9.11% complete · 1,004 units
As master developer
Dubai Land Department, 1 Nov 2026
DLD's project register names Emaar as master developer of 96 projects by other developers, in these communities:
- Dubai Marina52 projects by other developers
- Downtown Dubai30 projects by other developers
- Dubai Hills Estate13 projects by other developers
- The Greens1 project by other developers
Escrow banks used
Dubai Land Department, 1 Nov 2026
The banks holding the escrow accounts of projects by Emaar, with the number of projects each, from DLD's project register.
- Dubai Islamic Bank66 projects
- Mashreq66 projects
- Emirates NBD55 projects
- Abu Dhabi Commercial Bank53 projects
- First Abu Dhabi Bank43 projects
- Emirates Islamic24 projects
- Commercial Bank of Dubai14 projects
- Noor Bank6 projects
- RAKBANK4 projects
- Abu Dhabi Islamic Bank1 project
Source: Dubai Land Department project register (Projects and Developers files of 1 Nov 2026); sales from Dubai Land Department transactions, analysed by DataDXB. Communities are DataDXB's reviewed community names; where there is none, DLD's master project or area. Not an official DLD publication.